Report 3-month duration test of prototype sub-size EHP stack

At the 3-month duration test, the final EHP stack design was tested at different operating conditions to prove their influence on the performance and long-time durability. During this
operation time, no significant stack component degradation considering sealing issues and performance decrease occurred, although the sub-size stack was stressed much more than
at normal steady operating conditions. The results can be found in this report.